Resources can have both standard and overtime pay rates .By default, Project uses these rates for the duration of the project .However, you can change a resource’s pay rates to be effective as of the date you choose .For example, you could initially set up a resource on January 1 with a standard rate of $40 per hour, planning to raise the resource’s standard rate to $55 per hour on July 1 .