Please find attached file with FCST pre-advise. Data prepared according to the capacity statement - 19k/week.
explanation to file:
Column A - Required Week - Jabil production week (please consider the Transit Time separately)
Column B - Demand inline Capacity - we consider Your weekly production capacity as 19k
Column C - Jabil Requirement out of Supplier Capacity - within the given weeks our requirement is above Your capacities - please check and prepare scenarios how our demand can be met, please indicate methods like:
- shift mode switch, from production 3 shift model to full 4 shift one
- demand level loading - slight pre-build, pull in
Please note, the FCST shown is for pre-allignment purpose only!
Waiting for Your Prompt Reply