Conclusion:
Material for trial run of suffix change parts
- If the 4M change is related to design change approved by SONY design/engineering department , STT will contact with SONY designer to get related materials.
- If the 4M change needs approval from STT, it’s handled by SSCS-CN procurement team. Pls. clarify the materials STT need first, and we have to inform/discuss with our procurement.
Besides, if STT needs many materials, STT can accept to contact with partners directly, once received the contact information of partner.
2) Follow up CAR for reject(cosmetic issue) from Test Run
STT has accepted to handle the reject detected in test run, with SONY engineering
directly and cc to SSCS-CN for information sharing.